Implementation of the Project at AO Razrez Berezovsky

Work on the construction and installation of an integrated plant for treatment facilities intended for discharged quarry water at AO Razrez Berezovsky is in progress.

Currently, the installation of 6 units of vertical clarifying filter housings and 2 units of flotation clarifier bodies has been completed.

Double jointing of the auxiliary tank and the sludge bunker continues.

In the near future, the installation crew will start applying anti-corrosion coating to the auxiliary tank and the sludge bunker.

Commissioning of treatment facilities will allow the Customer to purify the quarry waters to the required parameters.

berioza2.png (regular, 500x375)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

berioza1.png (regular, 500x185)

Reference.
The main activity of AO Razrez Berezovsky is mining, processing and sale of coal as well as reclamation of disturbed lands.